top of page

Mandurah Forum Shopping Centre

Mandurah Forum Shopping Centre
Mandurah Forum Shopping Centre
Mandurah Forum Shopping Centre

Mandurah Forum Shopping Centre

June 2016 – January 2017

$12.15 Million

This project consisted of the complete concrete structure of which included detailed earthworks, the supply and install of formwork, supply and placement of 12,470m3 concrete. These works consisted of strip and pad footings, in-situ ground slab of 24,748 m2, in-situ columns, lift & stair shafts, suspended slabs area of 24,160m2 of which 6.0mtr high strutting was required executed utilising a table formwork system that incorporated beams of various thicknesses and depths.

Brookfield Multiplex Constructions

bottom of page